What to Include in a Metal Recycling Machine RFQ

A useful metal recycling machine RFQ does more than ask for a price. It gives every supplier the same material, capacity, site and scope assumptions so the proposals can be compared without hidden differences. The strongest RFQ is specific about the feed and the finished output, then separates what the supplier must provide from what the buyer must prepare.

1. Describe the material, not only the machine type

State the metal type and physical form: plate, profile, pipe, bar, sheet, UBC cans, machining chips, turnings, mixed light scrap or a complete assembly. Include the largest routine piece, typical thickness or section, bulk density and any contamination such as oil, paint, moisture or non-ferrous attachments.

For variable streams, provide a normal mix and a worst-case mix. A baler, shear, shredder or briquetting press can be selected only when the difficult material is visible. Photos and a material sample are often more useful than a generic description such as “steel scrap.”

2. Define the required finished output

Specify what must leave the machine: bale dimensions and approximate weight, briquette diameter and height, shredded length, or cut length and section. State whether the output must fit a furnace, container, stack, conveyor or downstream customer specification.

Give the required production basis clearly: tonnes per hour, pieces per hour or tonnes per shift. Explain the operating pattern, including shift length, expected interruptions and whether the machine will run continuously or in batches. This prevents two suppliers from quoting different meanings of “capacity.”

3. Provide the site and utility envelope

Include the available floor length, width and height, floor loading, access route for the machine and lifting capacity. Mark the loading and discharge zones on a simple layout sketch. For large equipment, the installation bay and maintenance clearance may determine the model before the price does.

State the available voltage, frequency, phase, transformer capacity and any limitations on starting current. The normal quotation range is 200-480 V / 3 phase / 50-60 Hz or a documented custom arrangement, but the chosen motor configuration still needs a site-specific review. Add compressed air, water, drainage and dust-extraction requirements where relevant.

4. Set the scope boundaries

Ask each supplier to list everything included in the offer: machine, motor, hydraulic power unit, controls, guards, feeding equipment, discharge equipment, spare wear parts, documents and installation support. Then list the buyer's responsibilities, such as foundations, crane work, electrical cable, compressed air and local permits.

A metal baler, alligator shear or briquetting press can appear cheaper only because a necessary conveyor, control panel or discharge arrangement is excluded. Scope clarity is more valuable than a long list of optional accessories.

5. Require safety and control details

Ask for the control philosophy, emergency-stop arrangement, guarding, access restrictions and maintenance isolation method. Identify who will operate the machine, what training they need and how faults will be displayed. For automated lines, define the start/stop sequence and the expected response to a jam or overload.

Include any site-specific electrical or safety standard the equipment must follow. Do not assume that a CE mark, IEC reference or general voltage range covers every project requirement. The final technical scope should state the applicable standard and the evidence supplied with the machine.

6. Plan shipping, installation and documentation

Provide the destination, nearest port, unloading capability and any container or weight restrictions. Ask for the shipping split, approximate dimensions and lifting points. Large lines may require several containers, and the site crane plan should be confirmed before shipment.

Request the operating manual, electrical drawings, hydraulic diagram, spare-parts list, foundation or loading information and commissioning checklist in the quotation stage. Confirm the language and format of the documents so the maintenance team can use them after delivery.

7. Compare proposals on the same matrix

A comparison sheet should include the model, published capacity, material limits, power, dimensions, weight, included equipment, control scope, safety devices, spare parts, documents, delivery and exclusions. Require each supplier to state the assumptions behind its capacity and configuration.

The downloads page provides current technical sheets for the published machine range. Use those documents to check model names, product links and released figures before comparing commercial offers.

RFQ checklist

  • Material type, form, largest piece and normal/worst-case mix.
  • Required output and operating hours.
  • Finished bale, briquette or cut dimensions.
  • Floor plan, access, lifting and maintenance clearance.
  • Voltage, starting current and connected power.
  • Included and excluded equipment.
  • Safety standard, controls and training.
  • Shipping, installation, documents and spares.
  • Acceptance criteria and commercial assumptions.